Two classrooms, four weeks, delivered before the new term.
St Nicholas Primary School sits at the centre of the village of Taplow, and any new building on the site needed to complement its surroundings. The brief called for two auxiliary classrooms within a 30m² structure, with app-controlled heating suitable for year-round use, all delivered within a fixed budget and with consideration for the character of the setting.
Primrose was instructed in early July. The project included construction, landscaping and an accessible path, with handover completed before the end of August.
Completed in 2023, this 30 m² project cost £44,000 excluding VAT, including the accessible path, approximately £1,467/m² excluding VAT. This is a historical project cost; current quotations may differ.
Local, experienced and focused on educational projects.
Educational settings often have demanding schedules and fixed handover dates. Primrose works with schools to coordinate project programmes around their operational requirements, with clear communication throughout.
With landscaping and accessibility considered as part of the overall project, the classrooms were delivered with an accessible route from day one, providing the school with a more complete and ready-to-use facility.
Primrose Projects delivered the full internal refurbishment of the Bayswater College campus in central London, transforming the existing premises into a modern learning environment for international students.
Primrose transformed an unused caretaker's house into a modern educational facility housing six dedicated classrooms for one-on-one and small-group teaching. The Tailor Provision was designed to support a more personalised, student-centred teaching model delivered within a demanding six-month timeline from conception to occupation.
Every Primrose room starts with a conversation. Tell us about your garden, your ideas and your budget — and we’ll tell you exactly what’s possible. No obligation, no pressure.