Bengeworth CE Academy
LOCATION
Evesham, Worcestershire
SECTOR
Education
CONSTRUCTION
SIPs, built on site
PUPILS
Up to Key Stage 2
Bengeworth CE Academy needed a dedicated environment for children who benefit from learning in smaller groups. Primrose created a 54 m² Inclusion Hub at the school’s Kings Road campus in Evesham, providing space for small-group teaching and interventions for pupils up to Key Stage 2.
The school appointed Primrose through a competitive tender process involving predominantly modular building providers. Our director-led approach and competitive pricing gave the client confidence that we could deliver the best outcome for its needs.
INSIDE THE HUB
Designed Around School Life.
A bubble tower and sensory carpet provide resources for supported sensory activities, while air source heating and cooling maintain comfort throughout the year.
Inside the Hub
- Main classroom
- Washroom
- Classroom sink
- Coat and bag storage
- Separate sensory calm space
A fabric-first approach
Structural insulated panels (SIPs) form the basis of a fabric-first approach, prioritising insulation and the performance of the building envelope to support long-term value.
54m2
Gross internal floor area
6weeks
Summer holiday programme
3days
Finished before term began
£170k
Approx. value inc. VAT
Programme
Completed Within The Summer Holidays.
May 2026
PROJECT AWARDED
First day of the holidays
CONSTRUCTION BEGINS
Six weeks
WITHIN THE PROGRAMME
Three days before term
COMPLETED
Awarded in May 2026, construction began on the first day of the summer holidays. Careful planning and an experienced team kept the project within its six-week programme, with completion three days before the holidays ended.
Building on site also gave the school flexibility to refine internal arrangements and finishes during delivery. Glazing was agreed early, with subsequent decisions coordinated around the construction programme.
An initial £5,000 deposit was followed by payments linked to physical progress on site, avoiding a large advance payment for manufacture.
Time-lapse
Watch It Come Together.
BEYOND THE BUILD
A Learning Opportunity For Pupils.
The project included a session delivered by Primrose director Sean Carter, showing pupils how their new Inclusion Hub was built. Children explored the materials and construction process, then watched the time-lapse video bringing the whole build together.
Start Your Project
Could we build something
like this for you?
Every Primrose room starts with a conversation. Tell us about your garden, your ideas and your budget — and we’ll tell you exactly what’s possible. No obligation, no pressure.