Steel frame for conservatory complete in Maida Vale

Primrose have completed the steel frame for a design and build conservatory in a Victorian townhouse. The job also comprises of internal refurbishment and new structural openings. Primrose are progressing at a good rate and hope to complete in four weeks time. Keep an eye out for more articles to come shortly.

Fit-out stage in Hounslow

The 2nd fix stage in Hounslow has begun, with the floor tiles being laid, the flat roof coverings going on and the glass being installed, Primrose are now very much ‘on the home staight’. Check in soon for more updates and articles.

Bathroom formed, Ground beam installed at Clapham.

Yesterday saw the erection of the stud partition to form the 1st floor bathroom.  The photo opposite  shows a ground beam which will be encased in concrete to bring the steel installation to completion. This project is progressing well without any any difficulties and is currently right on schedule.

Pond Excavation Underway at Farmhouse

Using a 3 tonne excavator and two dumpers, Primrose have begun to form the foundations for the 400 cubic metre pond. The pond is part of a wider landscaping scheme which is to be completed in the second phase of the works and will also include 3 paddocks and a tennis court. On a rare Sunny day in January, the photo opposite gives […]

Work commences on Farmhouse project

Yesterday saw construction work finally begin on our farmhouse extension and refurbishment project in Buntingford. In collaboration with Granta Architects , the project consists of the construction of a two storey extension, plus cellar to the side of the property. A further extension over the existing garage, and a loft conversion will complete the proposed scheme and create a substantial family home. Look out […]

Phase 1 steel installtion complete

Today saw the final stage of phase 1 steel installation at the refurbishment project in Clapham. Once installed, this steel, which weighs over 400Kg, will support 2 floors of existing victorian masonary. The new open plan kitchen will benefit from full height folding and sliding doors and a frameless glass roof. Look out for more […]

Tender submitted for restoration works in Park Lane

Primrose have just submitted their offer to carry out works to a large residential building in the heart of London. The building was constructed in the 1920’s and is suffering from a condition know colloquially as ‘Regent’s Street desease’. The problem affects building constructed in the early half of the 20th century where a steel superstructure […]

Primrose awarded £300k farmhouse contract

Primrose have been successful in their bid for an exciting residential development of a substantial farmhouse in Buntingford. The construction phase is 6 months and will start in early January. The scope of works will include a three-storey side extension starting below ground with the new basement level serving as a games room. Another interesting […]